Success with Active Harmonic Filters
One of our large industrial customers needed to add more
electrical plant to their existing supply to meet production
demands. The problem was the 5th Harmonic was already close
to the G5/4 Limits. The solution was to install Active Harmonic
Filters with the new plant. The result was to virtually eliminate
the 5th Harmonic Current and thus prevent an increase in the
overall levels.
Resisting the Surge
A major construction company had a key area of concern with
respect to protection of IT & Data equipment. Having installed
UPS & Standby Generators, VAR were commissioned to survey
the main site and provide a scheme for the installation of
Transient Voltage Surge Suppression (TVSS). The units have
now been successfully installed at the head office and the
program is being rolled out to regional offices.
Safety First
At VAR Services Ltd we take safety seriously, whether visiting
customer sites or carrying monitoring or service work. To
ensure the use of safe working practices, our engineers attend
the IOSH-SPA health & safety course, as part of the Passport
to Safety Scheme. This has proved of particular interest to
our customers in the Food industry as the scheme incorporates
a specific food safety element.
|